A project to remodel an office area has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)

Activity

Duration

Predecessors

A

3 months

B

2 months

C

3 months

D

4 months

A, B

E

3 months

A

F

2 months

B, C

G

2 months

F

H

1 month

G

I

4 months

D, E, F

J

5 months

H

a) What are the critical path activities? (5 points) b) What is the project’s scheduled completion time? (5 points) c) What is the slack or float for Activity B? Show your calculations. (5 points) d) What is the slack or float for Activity C? Show your calculations. (5 points) e) What is the slack or float for Activity E? Show your calculations. (5 points) f) What is the slack or float for Activity H? Show your calculations. (5 points) (Points : 30)

Need a Professional Writer to Work on this Paper and Give you a 100 % Original Paper? Click Here and Get this Essay Done……………



Click here to order similar paper @Essaybay.net. 100% Original.Written from scratch by professional writers.

Leave a Reply

Your email address will not be published. Required fields are marked *